Skip to main content

What You Need to Know about Force Majeure in Light of the Coronavirus

With the outbreak of coronavirus disease 2019 (“COVID-19”), the disease caused by the novel coronavirus (“SARS-CoV-2”), companies across various industries are taking precautions, some of which inevitably will result in nonperformance of their contracts. For some, relief from nonperformance may be found in the contracts themselves in the form of a force majeure provision. For others, whose contracts do not contain force majeure provisions, defending a potential breach of contract will be more of an uphill battle. As the landscape of the coronavirus outbreak develops, we will continue to look at the virus’s impact in more depth. First, we consider several key introductory questions to help guide you in your decision making processes in the coming weeks.

(1) What is a Force Majeure Provision?

Generally, the concept of force majeure (fr. “superior force”) excuses contractual nonperformance “when such nonperformance is caused by unforeseen events beyond the control of both parties that either make contract performance impracticable or frustrate the purpose of such performance.”[1] Also known as “Acts of God” provisions, force majeure clauses typically excuse nonperformance of a contract for events such as “natural disasters such as floods, tornadoes, earthquakes and hurricanes and acts of people such as acts of terrorism, riots, strikes, wars and medical epidemics.”[2] In some contracts, pandemic events are specifically included as force majeure events, given that “a truly deadly pandemic . . . would be highly disruptive to all forms of commerce, including construction activity.”[3]

In order to invoke a force majeure clause, there must be a causal link between the force majeure event and the affected party’s failure to perform. Some force majeure provisions limit the impact of the event on the party by its distance or time. Moreover, a party may be required to show that it made a reasonable effort to mitigate the effects of the force majeure event. However, the failure to perform need not rise to the level of impossibility—performance must be commercially impracticable, unreasonable, or fundamentally at odds with the business of a party. If a force majeure provision does apply, the affected party is excused from its obligations under the contract for at least as long as the force majeure event continues, and termination of the contract may be possible if the force majeure event continues for an extended period of time. Generally, force majeure provisions also contain a notification provision, whereby the affected party must notify the other contracting party in a timely manner.[4]

(2) Does COVID-19 qualify as a Force Majeure Event?

For contracts that contain a force majeure clause, depending on the wording of the force majeure provision itself, COVID-19 will likely qualify as a force majeure event. Some force majeure clauses reference broader categories that qualify as force majeure events, and thereby excuse nonperformance, such as, “acts of God,” “acts of government,” or “other circumstances beyond the parties’ reasonable control.” Under any of these broader provisions, COVID-19 would likely qualify under such a force majeure provision because the current outbreak contains “a naturally occurring component (the virus itself) and a government action component (such as quarantines and other measures to contain the outbreak)[,]” both of which may be covered under a standard force majeure clause. Other force majeure provisions may specifically include provisions such as “epidemic” or “pandemic” or “natural disaster”. Typically, even if a force majeure provision contains specific provisions, there will be a catchall at the end; however, be aware of whether or not the jurisdiction governing your contract will invoke the rule of ejusdem generis, under which a court will not construe such a catchall to have its broadest meaning, but will rather narrowly interpret such a phrase to include only events or things of the same general nature of class as those specifically listed in the provision.[5]

According to the website for the Centers for Disease Control and Prevention (“CDC”), on January 30, 2020, the International Health Regulations Emergency Committee of the World Health Organization (“WHO”) declared the outbreak a “public health emergency of international concern” (PHEIC). On January 31, 2020, Health and Human Services Secretary Alex M. Azar II declared a public health emergency (PHE) for the United States to aid the nation’s healthcare community in responding to COVID-19. While the CDC, WHO and the United States government have not officially labeled the coronavirus outbreak as an epidemic or a pandemic, a step that would do little to quell panic, it appears that COVID-19 is being treated as an epidemic. The CDC defines an “epidemic” as an “increase, often sudden, in the number of cases of a disease above what is normally expected in that population.” The CDC has also pointed out that the current situation meets two of three criteria of a pandemic and warns that the outbreak will likely reach the level of a pandemic in the coming weeks or months. The CDC defines a “pandemic” as an “epidemic that has spread over several countries or continents, usually affecting a large number of people.” There are three general criteria for a pandemic: (1) a virus that causes illness, including illness resulting in death; (2) sustained person to person transmission; and (3) worldwide spread.

 (3) Is a government directive required for nonperformance under a contract?

While many force majeure clauses contain an “acts of government” provision, and a government directive (e.g., mandatory quarantines or travel restrictions) would likely trigger a force majeure provision, such action is not a requirement to enforce a force majeure clause as long as the event in question qualifies under another provision of the force majeure clause. As discussed above, COVID-19 will likely qualify as a force majeure event under most force majeure clauses.        

(4) What if there is no force majeure provision in your contract?

If your contract does not contain a force majeure provision, nonperformance may still be excused. For example, if the performing party’s principal purpose of the contract has been frustrated, the party may seek to suspend its performance under the frustration of purpose doctrine. Under this doctrine, if a party’s principal purpose in making a contract is frustrated by some unforeseeable event, which occurs by no fault of the party, the party may be able to suspend or terminate the contract.[6] Additionally, a party may seek excusal from performance under the doctrine of impracticability. Under the doctrine of impracticability, a party may be excused from performing if an event occurs that makes performance unfeasible. Such events are generally ones that the parties did not anticipate happening, and which could not happen for the contract performance to be sustainable. At least in the context of transactions conducted under the Uniform Commercial Code, a party wishing to be excused from performance under a theory of impracticability must demonstrate that performance “has been made impracticable by the occurrence of a contingency the non-occurrence of which was a basic assumption on which the contract was made.” Finally, a party may attempt to get its performance excused under the theory of impossibility, which allows a party to suspend or delay its performance if “a change of circumstance renders it impossible.”[7] This approach, however, may prove difficult because very few circumstances will render performance literally impossible for situations involving an outbreak.

(5) What should you be doing now?

Review your existing contracts. First, does your contract contain a force majeure clause? If so, look to see whether it contains any broad or specific provisions under which COVID-19 may fall. Depending on the specific language in your force majeure provision, you may wish to begin having discussions with your counter parties about the potential invocation of your force majeure provisions and how best to mitigate any possible impact of COVID-19. If the provision has a formal notice requirement, be certain to comply with that. If your contracts do not contain a force majeure provision, these conversations may still be fruitful, particularly where the principal purpose of any given contract may be frustrated or become impracticable due to the impacts of COVID-19.

With regard to any new contracts, because the contract would be entered into at a time when the potential risks of COVID-19 are well known, you may not be able to rely on a force majeure clause as an excuse for nonperformance. As such, other contract provisions should be considered in order to account for COVID-19’s impact on the performance of the contract. For example, when submitting a proposal for new work, consider including a provision that states the proposal is based on current information on availability of materials and labor and price, and reserve the right to amend the proposal prior to acceptance due to any changes resulting from the impacts of COVID-19.


[1] Philip L. Bruner & Patrick J. O’Connor, Jr., Bruner & O’Connor on Construction Law § 7:229 (West Group 2002) (internal quotation omitted); see also Princeton Homes, Inc. v. Virone, 612 F.3d 1324, 1322 (11th Cir. 2010) (stating that a force majeure clause will cover “events that may or may not happen, but whether they do is beyond the control of [either] party”).

[2] Mark R. Vespole & Christopher H. Westrick, LexisNexis Practice Guide New Jersey Construction Litigation § 4.32 (Matthew Bender 2016).

[3] See Bruner & O’Connor, supra note 1 at § 7:230.52. The section discuses SARS as a force majeure event, and indicates that SARS killed 395 people as of May 1, 2003. See id. § 7:230.52. n. 15. COVID-19 has already killed 2,100 people, and infected at least 75.000 across 27 countries. See Alyn Woodward, The New Coronavirus has killed nearly 3 Times as Many People in 8 Weeks as SARS Did in 8 Months. Here’s How the 2 Outbreaks Compare, Bus. Insider (Feb. 20, 2020). 

[4] See SNB Farms, Inc. v. Swift & Co., 2003 U.S. Dist. LEXIS 2063, *29-30 (N.D. Iowa Feb. 7, 2003).

[5] See Bruner & O’Connor, Jr., supra note 1 § 7:229 (West Group 2002) (internal quotation omitted).

[6] Rembrandt Enters. v. Dahmes Stainless, Inc., 2017 U.S. Dist. LEXIS 144636 at *12 (N.D. Iowa Sept. 7, 2017); Voyager Communs. v. V HMW Communs., 1996 U.S. Dist. LEXIS 14447, at *4 (E.D.N.C. Aug. 21, 1996).

[7] See Impossibility of Performance, Bovier Law Dictionary (Wolters Kluwer 2012).

Subscribe To Viewpoints

Authors

Samuel M. Tony Starr

Member / Co-chair, Construction Law Practice

Samuel M. Tony Starr is a Mintz litigator and construction lawyer who works with contractors, owners, developers, and public authorities. He represents clients in significant construction litigation, arbitrations, and mediations. Tony frequently speaks on construction law developments.

Kaitlyn C. Leonard

Special Counsel

Kaitlyn C. Leonard is a litigator at Mintz who defends clients in matters involving product liability, construction accidents, insurance coverage, and other complex disputes.

Clare Prober

Associate

Clare Prober is a Mintz attorney who focuses on complex commercial litigation, contract disputes, and data privacy matters. They were a Mintz Summer Associate in 2018.